Eglinton Crosstown West Extension progress 2026 – just days after Toronto’s long-awaited Line 5 Eglinton Crosstown LRT opened on February 8, 2026, excitement is building for the next phase. This 9.2-kilometer westward push from Mount Dennis to Renforth Drive promises to transform transit in Etobicoke and beyond. If you’ve been following the main line’s saga (check out our detailed [Eglinton Crosstown LRT delays explained 2026] for that story), you’re probably wondering: How’s the Eglinton Crosstown West Extension progress 2026 shaping up? Is it on track, or facing similar hurdles? Let’s break it down – the good, the challenging, and what it means for your commute.
Understanding the Eglinton Crosstown West Extension: A Quick Overview
Imagine extending Toronto’s shiny new crosstown LRT farther west, bridging gaps in rapid transit and connecting more neighborhoods seamlessly. That’s the Eglinton Crosstown West Extension in a nutshell. This project adds 9.2 kilometers to Line 5, running mostly underground from the existing Mount Dennis Station, with an elevated section and surface touches near the end.
Key stops include Scarlett, Jane, Royal York-Eglinton, Islington-Eglinton, Kipling, Martin Grove, and Renforth – seven new stations in total. Renforth will link to Mississauga Transitway and GO buses, making regional travel easier. There’s even talk of a future phase to Pearson Airport, but that’s conceptual for now.
Why does this matter in 2026? With the main line fresh out of the gate, the Eglinton Crosstown West Extension progress 2026 builds on that momentum, aiming for a continuous LRT spine across the city.
The Timeline: Where Eglinton Crosstown West Extension Progress 2026 Stands Today
Projects like this don’t happen overnight – think of it as assembling a massive puzzle underground and above ground. Construction kicked off in July 2021 with advance tunneling, well before the original Crosstown’s delays dominated headlines.
Fast-forward to 2026: Major milestones have been hit. Tunneling wrapped up key segments in 2024 and 2025, elevated guideway work is ramping up, and station contracts are advancing. The target? Substantial completion around 2030-2031, with service starting shortly after.
No firm opening date yet – Metrolinx is cautious after the main line’s lessons – but Eglinton Crosstown West Extension progress 2026 shows steady movement. Unlike the original, this uses progressive design-build models to catch issues early.
Key Milestones in Eglinton Crosstown West Extension Progress 2026
What’s actually happening on the ground (and below it)? The Eglinton Crosstown West Extension progress 2026 highlights several wins that keep optimism high.
Tunneling Triumphs: Digging Deep for Success
Tunneling is the backbone – literally. Two massive tunnel boring machines (TBMs) chewed through earth, completing twin tunnels for much of the route. By mid-2024, one contract finished; the second followed in 2025. Breakthrough moments, with crews celebrating as TBMs emerged, marked huge steps.
These tunnels connect smoothly to Mount Dennis, ready for tracks and systems. It’s like carving secret highways underground – quiet, efficient, and minimally disruptive above.
Elevated Guideway: Rising Above Challenges
One of the coolest features? A 1.5-kilometer elevated section crossing the Humber River valley. Work here exploded in 2025-2026, with piers going up and guideway segments installed.
Renderings show sleek, modern structures blending into the skyline – think smooth rides with views over greenery. This avoids deep digs in sensitive areas, speeding things up.
Stations and Systems: The Heart of the Extension
Seven new stations are in procurement phases. In 2025, partners were selected for design and build – expect modern, accessible hubs with art integrations and bike facilities.
Rails, signals, and systems contracts are progressing separately to avoid bottlenecks seen in the main line. Early 2026 updates from Metrolinx highlight “major progress” across the board.

Budget and Funding: Counting the Costs of Eglinton Crosstown West Extension Progress 2026
Money talks in big infrastructure. The Eglinton Crosstown West Extension is budgeted around $4.7 billion, with some estimates at $3-4 billion for the core phase. Funding comes from provincial and federal sources, part of Ontario’s massive transit push.
So far, no massive overruns reported – a relief after the original line’s ballooning costs. Transparent reporting and phased contracts help keep Eglinton Crosstown West Extension progress 2026 on financial track.
Community and Environmental Impact
Construction isn’t painless. Residents along Eglinton West deal with noise, traffic shifts, and detours – but Metrolinx emphasizes mitigation, like noise walls and community updates.
On the plus side? Greener transit means fewer cars, better air quality, and transit-oriented development boosting local economies. Stations will spur housing and jobs, revitalizing areas.
Lessons Learned: Avoiding Past Pitfalls in Eglinton Crosstown West Extension Progress 2026
The main Crosstown’s delays taught hard lessons – defects, disputes, integration woes. For the west extension, Metrolinx switched gears: Separate contracts for tunneling, guideway, and stations allow parallel work and risk sharing.
More oversight, proactive testing, and flexible models aim to deliver on time. As of 2026, it seems to be working – steady Eglinton Crosstown West Extension progress 2026 without major public dramas.
The Future: What Eglinton Crosstown West Extension Progress 2026 Means for Toronto
By 2031, picture hopping on Line 5 from Kennedy all the way to Renforth – or beyond if airport plans materialize. Faster commutes, reduced congestion, and stronger links to Mississauga and Pearson.
Early riders on the main line rave about reliability; the extension will amplify that. Have you ridden the Crosstown yet? The west leg will make it even more indispensable.
Conclusion: Optimism for Eglinton Crosstown West Extension Progress 2026 and Beyond
The Eglinton Crosstown West Extension progress 2026 paints a promising picture: Tunnels done, guideways rising, stations advancing toward a 2031 opening. Learning from past delays, this phase prioritizes smarter delivery for Toronto’s growing needs. Whether you’re in Etobicoke or just love good transit, this extension is worth watching. Toronto’s rapid transit future looks brighter – get ready for more smooth rides ahead.
Frequently Asked Questions (FAQs)
What is the current status of Eglinton Crosstown West Extension progress 2026?
As of early 2026, tunneling is largely complete, elevated guideway construction is underway, and station designs are progressing toward a 2030-2031 opening.
When will the Eglinton Crosstown West Extension open based on 2026 progress?
Metrolinx targets 2031 for service start, with major works like tunneling already finished and no significant delays reported so far.
How long is the Eglinton Crosstown West Extension and how many stations?
It’s 9.2 kilometers with seven new stations, extending Line 5 from Mount Dennis to Renforth Drive.
Will the Eglinton Crosstown West Extension connect to Pearson Airport?
The current phase ends at Renforth, but conceptual plans exist for a future extension to the airport.
How does Eglinton Crosstown West Extension progress 2026 differ from the main line’s delays?
Separate contracts, early starts on tunneling, and lessons from defects/disputes help keep this phase on a smoother path.